Virginia Beach NOI Recovery Plan

Closing the gap to budget — owned, item by item

Top Line Revenue

Sales beat budget by $62,314 (+26.14%) in August — Dumps , fuel , and OT are still clear opportunities for us.

Resi AJS

Jimmie
Where we are
65.70% vs 66.00% target (-0.30pt, Power 6 Jul MTD)
Last year
71.9% was the resi last month
The plan
Intentional pairing with Seniors in the business to train below standard route leaders in order for every certified teammate is able to maximize every job.
By when
First two weeks of September we will be able to roll out a system week to week with priority pairing per SSL in order to get guys tightened up.

Resi Cancel

Jimmie
Where we are
40.1% vs 36.00% target (-4.1pt, Power 6 Aug MTD)
Last year
39.5%
The plan
Ensuring that “Basic Standard Protocol” is followed during negotiations. (OPS included as well)- ensuring collisions happen when standard is not followed. REEAP morning meeting training 5 days a week.
By when
First week of October

Ground Game

Where we are
4.00 points per
Last year
awaiting numbers
The plan
Not dispatching a job until we verify ground game every two jobs of min 10pts. It starts with holding the line.
By when
First week of september.

Labor

COGS Wages ran $17,156 over budget in August. Offset by OT finishing under plan , wages also decreasing.

RPH / OT

Jaquan/Casey
Where we are
OT $8,461 actual vs $4,600 budget (-5.0%, under) —
Last year
OT $2,180 vs 4,600 budget ( + 1,693 ) .
The plan
Sending help to larger jobs , scheduling swings in order to help with the cutting teams going to the dump. Complete shift changes , brining in enough crews to eliminate over saturation 10+ hour day.. Every two week conclusion based on RPH , along with morning training around on site processes. During schedule calls in the afternoon, setting up routes with intentionality, utilizing new meeting checklist
By when
First week of October

COGS

Fuel & Dumps did the most damage in August $72,817 over budget (+62.44%); dump was roughly high.

Dump / Metal

Jaquan & Casey
Where we are
Dump $55,011 vs $36,723 budget (+33%, ~flat) · Metal $2,670 vs $1,067 ( + 1,603 )
Last year
Dump - $27,565 vs $36,723 ( $9,158 ). Metal - 0%
The plan
Introducing Metal and Donation recycling contest , to invite more contribution from the teams. Deep diving into pictures per every job. Utilizing metal recycling through the day , and coaching teams to restacking/breaking down items in truck from the pictures. Forming a mattress plan for the EOD process. (Spent over 4k in mattresses last month)
By when
Start of October

Fuel

Jaquan
Where we are
$17,806 actual vs $11,042 budget (+0.76 )
Last year
Last year 2.76% ($11,386) vs 2.4% budget
The plan
WC completion by 5pm for the jobs next day to ensure , planning for routes ( Confirming what’s a tp , cancel , and just an estimate. )and maximization is to the fullest. Limit Idling , with collision based conversations around multiple infractions.
By when
First two week of October.

Where we are
awaiting numbers
Last year
awaiting numbers
The plan
awaiting numbers
By when
awaiting numbers

OT — Certified teammates above the line

OWNER - Jimmie

WHERE WE ARE
OT - .88 ( 4,597 ) VS 1% budget ( 5,000 ) CTAL - July 42% , August 68% VS standard of 75%
THE PLAN
LAST YEAR
OT above the 1% at vs 1.29% ($6,693) CTAL - July 75% , August 77%
Live from the working Slides deck — Oct 23, 2026, 3:33 PM ET. Edit the deck, refresh this page, see it here.